Industrial Fan Manufacturing · Zibo, China
QIYUE FAN industrial fan manufacturer
Menu

QIYUE FAN · FAN-TO-DUCT INTERFACES

Fan Flexible Connector RFQ: Close the Interface Gaps Before Ordering

A quotation that says “flexible connection included” can still leave an installation team missing a mating flange, attachment hardware or an approved material. Treat each inlet and outlet connection as a separate interface, with its own drawing, duty and supply boundary.

Buyer takeaway: identify what connects to what, under which conditions, and who supplies every part. Agree the connector and accessory scope in the quotation.

One interface, three separate approvals

Fan side

Fan nozzle / flange
↓
Connection detail

Reference the inlet or outlet tag and approved fan drawing. Record the actual end connection, not just the nominal fan model.

Duct side

Connection detail
↓
Mating duct / transition

Reference the mating drawing and installation owner. Keep connector selection, duct support and installation acceptance responsibilities explicit.

Conceptual review map only. It does not show an assembled joint, support design, installation gap or approved dimensions.

1. Freeze the geometry before comparing prices

Use one marked drawing for both mating sides. Ask the supplier to return a connection detail identifying the joint type, dimensions and attachment method. Do not substitute a catalog photograph for a checked interface.

  • Identify inlet or outlet, equipment tag and drawing revision.
  • Record round or rectangular geometry and the applicable dimensions.
  • For a bolted joint, request the mating flange and hole-pattern details. For a sleeve connection, request the approved end and attachment details.
  • Ask the responsible designer to specify the installed span and permitted movement or offset, if any. Do not invent a universal gap.

Why separate the parts? The Greenheck QEI/QEI-M/QEID manual, Duct Connections illustrates different slip-fit and flanged arrangements and separately identifies sleeve and hardware scope. Use the selected equipment’s connection drawing and bill of materials for your order.

2. Request suitability for the actual duty

Pressure and temperature

State the pressure conditions at the connection, with units and sign/reference. Provide normal and relevant extreme temperatures, including the duration of intermittent exposure. Request the connector supplier’s acceptance for those conditions.

Medium and exposure

Describe the conveyed medium and known constituents, plus indoor or outdoor exposure. Ask for material and joint suitability evidence; a fan casing material does not establish connector compatibility.

The Carlisle HVAC flexible-connector technical guidance identifies pressure, temperature, environment, airstream constituents and span as selection inputs. It also warns that excessive fabric droop or folding can affect airflow. Use the selected product’s instructions, not generic fabric ratings or a visual guess.

Where the project has fire, hazardous-area or other special requirements, name them in the RFQ and request product-specific evidence from the responsible party. Do not assume a general-purpose flexible connector meets those requirements.

3. Close the supply boundary line by line

Use included / optional / excluded / by others / pending for each item. “Pending” is preferable to silently assuming it is in the fan price.

Physical parts

Connector assembly, mating flanges or end fittings, clamps or fasteners, sealing components and any specified accessories. Ask for quantities and the relevant drawing or part reference.

Engineering and handover

Material confirmation, interface approval, installation instructions, support-design owner and acceptance record. Name the party that resolves a mismatch before fabrication or installation proceeds.

Have the equipment and system designers confirm the joint’s function, alignment, load support and any expansion-joint requirements. A vibration complaint still needs its own diagnosis; see the fan vibration review.

Copy one record for each connection

Project / fan tag:
Interface: inlet / outlet / other:
Fan-side drawing and revision:
Duct-side drawing and revision:
Joint type and mating dimensions:
Installed span / movement requirement and design owner:
Pressure conditions, units and reference:
Temperature range and intermittent exposure:
Medium, constituents and environmental exposure:
Connector product / material evidence:
Parts included / optional / excluded / by others:
Installation and support-design responsibility:
Open mismatch, owner and approval reference:

Use this record alongside the general arrangement drawing review and quotation comparison guide. Do not release an unresolved interface on the assumption that the site team can make it fit.

Review the connection with the fan package

Send the marked fan and duct drawings, available duty data and proposed accessory scope. Supply availability and compatibility must be confirmed for the actual project.

Send interface information →